An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?
Answer: B
Explanation
Accelerating a project fundamentally changes its risk profile. Schedule compression introduces new risks (quality issues, resource strain, missed deadlines) and alters existing ones. The risk management plan is the guiding document that defines how risks will be identified, analyzed, monitored, and controlled. Revising it ensures the risk manager adapts the framework to the new project conditions before taking tactical steps. Once the plan is revised, the risk manager can then: Update the risk register with new risks (Option C). Engage stakeholders to communicate changes (Option D). Assess resource sufficiency (Option A). Why not the other options:
- A. Ensure sufficient resources are available ? Important, but this is a reactive step. Without revising the plan, resource allocation may not align with the updated risk strategy.
- C. Update the risk register ? This comes after the plan is revised, since the register is based on the plan’s framework.
- D. Meet with stakeholders ? Necessary, but the risk manager should first have a revised plan to guide stakeholder discussions. ???? PMI exams often test whether you recognize the structured order of risk management activities. The plan always comes first when project conditions change.