PRINCE2 PRINCE2

PRINCE2 Prince2-Practitioner Exam Dumps

PRINCE2 7 Practitioner (7th Edition) Exam

Exam code
Prince2-Practitioner
Questions
293
Updated
25 Nov 2026
  • Instant access from My Account after payment
  • 90 days of free updates
  • Money-back guarantee – see conditions
  • Help by live chat or email
Choose a format
Try free sample questions

Prices in USD. Downloads appear in My Account once your order is complete.

  • Instant access from My Account after payment
  • 90 days of free updates
  • Money-back guarantee – see conditions
  • Help by live chat or email
Free demo

Prince2-Practitioner sample questions

Check the style and quality of the material before you buy.

Question 1

Which of the following statements is NOT correct?The Learn from Experience principle suggests that lessons should be actively sought...

  • A. When Starting a Project
  • B. When Initiating a Project
  • C. As the project progresses
  • D. As the project closes

Answer: B

Question 2

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that the project has been closed prematurely and has not achieved the objectivesdefined in the Project Initiation Documentation (PID)?

  • A. Benefits Review Plan
  • B. End Project Report
  • C. Exception Report
  • D. Project closure notification

Answer: B

Question 3

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that without the calendar the company is going to experience difficultiesrecovering its decline in orders, and alternative solutions are required if the company is going to recover itsposition?

  • A. Benefits Review Plan
  • B. Exception Report
  • C. End Project Report
  • D. Risk Register

Answer: C

Question 4

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that the staff photo sessions were disruptive to the Engineering Department asthey had been scheduled during peak work times without consultation with the Engineering Manager?

  • A. Follow-on action recommendations
  • B. Lessons Report
  • C. Project closure notification
  • D. Risk Register

Answer: B

Question 5

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that if anybody has any remaining resource costs to be charged to the project, theyshould ensure this is done by 10 November?

  • A. Benefits Review Plan
  • B. End Project Report
  • C. Follow-on action recommendations
  • D. Project closure notification

Answer: D

Question 6

Which of the following principles describes this statement?"xxx defines tolerances for each project objective to establish limits of delegated authority"

  • A. Manage by stages
  • B. Focus on products
  • C. Manage by exception
  • D. Learn from experience

Answer: C

Question 7

Which of the following statements is FALSE regarding the Continued Business Justification?

  • A. The justification for the project must remain the same throughout the project
  • B. The justification for the project should remain valid
  • C. The justification for the project may change
  • D. If the project is no longer justified it should be stopped

Answer: B

Question 8

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

  • A. Issue Register
  • B. Follow-on action recommendations
  • C.Lessons Report
  • D. Risk Register

Answer: C

Question 9

It is now late October and the project is in stage 3. The label design competition has been held and the photosof the staff have been taken. The CEO and Marketing Director still need to choose the winning label designand the 12 photos for the calendar. However, the Executive has learned that two competitors are issuingcalendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of theoptions the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to beclosed now.Which product should show that the photos could be used for other promotional material for the company?

  • A. Benefits Review Plan
  • B. Lessons Log
  • C. Exception Report
  • D. End Project Report

Answer: D

Question 10

Which of the following principles uses Product Descriptions to provide clarity by defining each product'spurpose, composition, derivation, format, quality criteria and quality method?

  • A. Tailor to suit the project environment
  • B. Focus on products
  • C. Manage by stages
  • D. Continued business justification

Answer: B

Why Dumpsforsure is the best choice for PRINCE2 Prince2-Practitioner exam preparation

Secure your position in a competitive IT industry

The PRINCE2 Prince2-Practitioner certification is a strong way to demonstrate your understanding and ability. Our Prince2-Practitioner questions & answers help you prepare for it, so you can secure your current position and move your career forward.

Reviewed by IT professionals

We keep our Prince2-Practitioner exam dumps up to date, with explanations. The questions and answers on Dumpsforsure are reviewed by people with professional experience of PRINCE2 technologies.

One place to prepare

Dumpsforsure brings together the material you need for the PRINCE2 Prince2-Practitioner exam. Explanations are added to the questions to help you understand the logic behind them and prepare for other PRINCE2 exams.

Updated Prince2-Practitioner questions & answers

We update the exam files regularly to add new questions. The date of the latest update is shown at the top of this page.

Free Prince2-Practitioner demo before you buy

You can view sample Prince2-Practitioner questions on this page before buying, to see the format and pattern of the material.

90 days of free updates

You are eligible for 90 days of free updates after buying the Prince2-Practitioner exam. If the file is updated in that time, you can download the latest version from your account.

Ready to prepare?

PRINCE2 Prince2-Practitioner · 293 questions

Choose a format