SAP SAP Certified Application Associate

SAP C_TS412_2021 Exam Dumps

SAP Certified Application Associate - SAP S/4HANA Project Systems

Exam code
C_TS412_2021
Questions
110
Updated
25 Nov 2026
  • Instant access from My Account after payment
  • 90 days of free updates
  • Money-back guarantee – see conditions
  • Help by live chat or email
Choose a format
Try free sample questions

Prices in USD. Downloads appear in My Account once your order is complete.

  • Instant access from My Account after payment
  • 90 days of free updates
  • Money-back guarantee – see conditions
  • Help by live chat or email
Free demo

C_TS412_2021 sample questions

Check the style and quality of the material before you buy.

Question 1

You have saved a network and activates with assigned material components. As soon as you releasethe network, you receive the error message "Business transaction cannot be carried out" What couldbe the reason for this error message?

  • A. Missing budget for material components
  • B. Missing reservations for material components
  • C. Missing material availability
  • D. Missing authorizations to release material components

Answer: D

Explanation

One possible reason for the error message "Business transaction cannot be carried out"? when releasing a network is missing authorizations to release material components. Material components are materials that are required for executing a network activity. To release material components, you need to have the authorization object C_AFKO_ATY with the activity 02 (change) for the order type of the network. Reference: https://answers.sap.com/questions0952/the-business-transactioncannot%02be-carried-out-mes.html

Question 2

Your customer has created networks with internal activities and generated capacity requirements.Now, they want to analyze the capacity requirements of their project. Which report do yourecommend?

  • A. Individual overview capacity requirements
  • B. Capacity load work center view
  • C. Extended capacity evaluation
  • D. Structure overview

Answer: C

Explanation

To analyze the capacity requirements of their project, you can recommend using the extended capacity evaluation report. The extended capacity evaluation report displays capacity requirements and availability for work centers or resources over a period of time. You can use various selection criteria and display options to customize the report according to your needs. You can also access detailed information on individual capacity requirements or availability situations by choosing drilldown functions. Reference:

Question 3

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you wantto define a milestone for February 10 which should NOT be changed through scheduling. What doyou recommend for milestone definition?

  • A. Enter an offset of -18 days to the finish date of the activity
  • B. Enter February 10 as fixed date
  • C. Enter 10 days as duration
  • D. Enter an offset of 10 days to the start date of the activity

Answer: B

Explanation

To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding activities or milestones. A fixed date can be entered manually or automatically derived from a constraint.

Reference

Question 4

You want to create a reservation for a material component assigned to a network activity.However, after releasing and saving the activity, no reservation is created. What are some possiblereasons for the missingreservation?Note: There are 2 correct answers to this question

  • A. The availability check for material components indicates missing parts
  • B. The material master is set to external procurement
  • C. The indicator Reservation/Purchase Requisition indicator for the material component assigned tothe activity is set to "never"
  • D. The material is assigned to the activity as a non-stock material

Answer: C, D

Explanation

Some possible reasons for the missing reservation for a material component assigned to a network activity are: The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never"?, which means that no reservation or purchase requisition is created for the material component. The material is assigned to the activity as a non-stock material, which means that it does not have a stock record in inventory management and no reservation is created for it. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/en%02USa7a9f0a6e421014e10000000a174cb4

Question 5

What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to thisquestion

  • A. Location
  • B. Material
  • C. Production version
  • D. Resource

Answer: B, D

Explanation

PPIDS master data is necessary for using PP/DS, which is a component of SAP APO that provides advanced planning and scheduling functions for production planning and detailed scheduling. PPIDS master data includes material and resource data. Material is a set of data that defines the characteristics and properties of a product that can be produced or procured. Resource is a set of data that defines the characteristics and capacities of a production facility that can be used to produce products. Reference: https://help.sap.com/doc/saphelp_scm700_ehp02.0.2/en%02US/f3055130534338e10000000a154ce5/content.ht

Question 6

How can you record external service activities with service master data? Note: There are 2 correctanswers to this question

  • A. Confirm the network activity for external service
  • B. Confirm the activities in the Cross-Application Time Sheet (CATS)
  • C. Post a goods receipt in the goods movement application (MIGO)
  • D. Create a service entry sheet

Answer: BD

Explanation

To record external service activities with service master data, you can confirm the activities in the Cross-Application Time Sheet (CATS) or create a service entry sheet. Service master data is a set of data that defines the scope and details of a service to be performed by an external vendor for a project activity. Confirming the activities in CATS is an action that records the time spent on performing external services and posts actual costs to the project. Creating a service entry sheet is an action that records the delivery of external services and posts actual costs to the project. Reference:

Question 7

Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers tothis question.

  • A. Usage of cost elements is mandatory
  • B. Sales prices are maintained in the DIP profile
  • C. DIP is used to create a quotation
  • D. Sources can be based on line items
  • E. Material determination is mandatory

Answer: BDE

Explanation

Dynamic item processor (DIP) is a tool that allows you to create sales order items automatically based on project data. Some of the features of DIP are: Sales prices are maintained in the DIP profile, which is a parameter that defines how sales order items are created and priced from project data. Sources can be based on line items, which means that you can use individual cost elements or revenue elements as sources for creating sales order items. Material determination is mandatory, which means that you have to assign a material number to each source in order to create sales order items. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/en%02USa7a9f0a6e421014e10000000a174cb4.html

Question 8

Which of the following actions can transfer actual costs for external processing? Note: There are 2correct answers to this question

  • A. Saving a supplier invoice
  • B. Saving a service entry shee
  • C. Saving a goods receipt
  • D. Saving a purchase order

Answer: AB

Explanation

Saving a supplier invoice and saving a service entry sheet are some of the actions that can transfer actual costs for external processing. External processing is a process that involves procuring services from external vendors for project activities. Saving a supplier invoice is an action that records the payment request from a vendor for the services performed and posts actual costs to the project. Saving a service entry sheet is an action that records the delivery of services from a vendor and posts actual costs to the project. Reference:

Question 9

Which of the following factors influence the scheduling of internal processing activities? Note: Thereare 3 correct answers to this question

  • A. An activated Scheduling indicator in the control key of the internal processing activity
  • B. Whether the work for the internal activity is greater than its duration
  • C. The unit (for example, hour, day) of the field Normal Duration field of the activity
  • D. The relationships between activity elements
  • E. The factory calendar in the work center used for the internal processing activity

Answer: A, D, E

Explanation

The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The scheduling indicator in the control key determines whether an activity is included in scheduling or not. The activity elements are subordinate units of an activity that represent partial tasks or work packages. The relationships between activity elements define the logical sequence and dependencies of the partial tasks. The factory calendar is a parameter that defines the working days and holidays for a work center. The factory calendar affects the duration and dates of an activity that uses the work center. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/en%02USa7a9f0a6e421014e10000000a174cb

Question 10

Which of the following statements apply to project versions? Note: There are 2 correct answers tothis question

  • A. Project versions can be changed
  • B. Project versions are mandatory for Milestone Trend Analysis (MTA)
  • C. Project versions can be created automatically based on user status
  • D. Manually Created project versions always require a project version profile

Answer: B, C

Explanation

Project versions are copies of projects that allow you to save snapshots of project data at different points in time. Project versions are mandatory for Milestone Trend Analysis (MTA), which is a tool that allows you to monitor and compare the planned and actual dates of milestones in a project over time. Project versions can be created automatically based on user status, which means that you can define rules that trigger the creation of project versions when certain user statuses are set for project objects. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/en%02USa7a9f0a6e421014e10000000a174cb4.html

Why Dumpsforsure is the best choice for SAP C_TS412_2021 exam preparation

Secure your position in a competitive IT industry

The SAP C_TS412_2021 certification is a strong way to demonstrate your understanding and ability. Our C_TS412_2021 questions & answers help you prepare for it, so you can secure your current position and move your career forward.

Reviewed by IT professionals

We keep our C_TS412_2021 exam dumps up to date, with explanations. The questions and answers on Dumpsforsure are reviewed by people with professional experience of SAP technologies.

One place to prepare

Dumpsforsure brings together the material you need for the SAP C_TS412_2021 exam. Explanations are added to the questions to help you understand the logic behind them and prepare for other SAP exams.

Updated C_TS412_2021 questions & answers

We update the exam files regularly to add new questions. The date of the latest update is shown at the top of this page.

Free C_TS412_2021 demo before you buy

You can view sample C_TS412_2021 questions on this page before buying, to see the format and pattern of the material.

90 days of free updates

You are eligible for 90 days of free updates after buying the C_TS412_2021 exam. If the file is updated in that time, you can download the latest version from your account.

Ready to prepare?

SAP C_TS412_2021 · 110 questions

Choose a format