SAP SAP Certified Application Associate

SAP C_TSCM42_67 Exam Dumps

SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7

Exam code
C_TSCM42_67
Questions
106
Updated
25 Nov 2026
  • Instant access from My Account after payment
  • 90 days of free updates
  • Money-back guarantee – see conditions
  • Help by live chat or email
Choose a format
Try free sample questions

Prices in USD. Downloads appear in My Account once your order is complete.

  • Instant access from My Account after payment
  • 90 days of free updates
  • Money-back guarantee – see conditions
  • Help by live chat or email
Free demo

C_TSCM42_67 sample questions

Check the style and quality of the material before you buy.

Question 1

Which of the following structural elements does a process order have? (Choose three.)

  • A. Item data
  • B. Parallel sequences
  • C. Relationships
  • D. Phases
  • E. Characteristic-based process instructions

Answer: C,D,E

Question 2

Which of the following statements best defines SAP ERP?

  • A. SAP ERP is an application that supports all processes involving direct customer contact throughout the entire customer relationship life cycle.
  • B. SAP ERP is an application that a company can use to manage its business processes efficiently.
  • C. SAP ERP is a system in which advanced planning and optimization processes can be mapped.
  • D. SAP ERP is a system hardware that includes components such as Purchasing, Sales and Distribution, Materials Management, and Production.

Answer: B

Question 3

Which activity can trigger an automatic availability check for the components of a production order?

  • A. Material staging
  • B. Order rescheduling
  • C. Order release
  • D. Goods receipt for a missing part

Answer: C

Question 4

Which of the following statements about the planning functions available in SAP ECC is correct?

  • A. Master production scheduling (MPS) refers to preferred planning of important materials.
  • B. Material requirements planning (MRP) includes automatic capacity leveling.
  • C. Long-term planning (LTP) is a long-term form of forecast planning.
  • D. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.

Answer: A

Question 5

The final assembly of a finished product should only be triggered when a customer order arrives.Which planning strategy for the finished product do you use?

  • A. Planning with make-to-stock (strategy 10)
  • B. Planning at the assembly level (strategy 70)
  • C. Planning without final assembly (strategy 50)
  • D. Planning with final assembly (strategy 40)

Answer: C

Question 6

Which of the following are characteristics of ECC master production scheduling (MPS)? (Choose three)

  • A. MPS items are planned in a standard MRP run.
  • B. The planning of MPS and non-MPS items is always carried out in one planning run.
  • C. Non-MPS items can be taken into consideration by an MPS run.
  • D. MPS items can be defined on plant level.
  • E. MPS items can be defined on MRP area level.

Answer: C,D,E

Question 7

What is SAP Solution Manager?

  • A. A transaction in the SAP ECC system
  • B. A standalone system that communicates with other systems in a system landscape
  • C. An add-on industry solution
  • D. A managed system in a system landscape

Answer: B

Question 8

For which of the following objects can you enter a confirmation? (Choose two)

  • A. Work Center
  • B. Production order operation
  • C. Production order
  • D. Trigger Point

Answer: B,C

Question 9

What do you have to consider regarding consumption? (Choose two)

  • A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
  • B. Consumption is restructured with the planning run.
  • C. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.
  • D. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.

Answer: C,D

Question 10

What can you use to organize material staging for production orders? (Choose three)

  • A. Material documents
  • B. Transfer orders
  • C. KANBAN
  • D. Pull list
  • E. Logistics Information System (LIS)

Answer: B,C,D

Why Dumpsforsure is the best choice for SAP C_TSCM42_67 exam preparation

Secure your position in a competitive IT industry

The SAP C_TSCM42_67 certification is a strong way to demonstrate your understanding and ability. Our C_TSCM42_67 questions & answers help you prepare for it, so you can secure your current position and move your career forward.

Reviewed by IT professionals

We keep our C_TSCM42_67 exam dumps up to date, with explanations. The questions and answers on Dumpsforsure are reviewed by people with professional experience of SAP technologies.

One place to prepare

Dumpsforsure brings together the material you need for the SAP C_TSCM42_67 exam. Explanations are added to the questions to help you understand the logic behind them and prepare for other SAP exams.

Updated C_TSCM42_67 questions & answers

We update the exam files regularly to add new questions. The date of the latest update is shown at the top of this page.

Free C_TSCM42_67 demo before you buy

You can view sample C_TSCM42_67 questions on this page before buying, to see the format and pattern of the material.

90 days of free updates

You are eligible for 90 days of free updates after buying the C_TSCM42_67 exam. If the file is updated in that time, you can download the latest version from your account.

Ready to prepare?

SAP C_TSCM42_67 · 106 questions

Choose a format